What changed
The rule revises 36 CFR part 218, the predecisional review process for covered Forest Service projects and activities analyzed through an environmental assessment or environmental impact statement.
That first stage is the opportunity to comment. The minimum period is 15 calendar days for an EA and 30 calendar days for an EIS. The clock starts the day after notice is published on a USDA website. The period cannot be extended, although a deadline that falls on a weekend or federal holiday moves to the next working day.
This second clock can begin when the agency posts a draft Finding of No Significant Impact for an EA or a draft Record of Decision for an EIS. Written objections are due within 10 days for an EA and 20 days for an EIS. The USDA website publication date is the exclusive source for calculating that deadline. The agency also says it will send notifications through tools such as email lists or subscription services, but those messages do not replace the date on the project page.
Why it matters
The result is a two-stage public record. A person or organization generally may object only after submitting timely, specific written comments during the earlier comment period. The later objection must generally connect its issues to those prior comments. The rule lists exceptions for matters such as modified or new alternatives, newly disclosed analysis, and science published after the comment period.
That sequence raises the cost of missing a notice. Someone who discovers a project only when the draft decision appears may already be ineligible to object. Someone who commented broadly may find that a later issue cannot be tied back to the original submission.
Behind the shorter windows is an explicit speed argument. The Forest Service says the existing process added minimum periods of roughly 120 to 150 days for an EA project and 135 to 165 days for an EIS project. The agency presents the revision as an efficiency measure. The tradeoff is a process that puts more weight on early attention, precise comments, and a preserved filing record.
Verification bottleneck
That record is only useful if the filing survives review. An entire objection must be set aside without review if it is late, comes from someone without qualifying prior comments, concerns the wrong project, or fails to meet the rule’s requirements. Individual issues can also be set aside if they are not linked to prior specific comments or do not identify a requested action or mitigation.
The format rules make that test concrete. Objections are limited to 15 pages for an EA and 30 pages for an EIS. A page entered through a web form counts as 500 words. Electronic files must use accepted formats and remain accessible for printing, copying, and screen readers. Ordinary web links included as supporting material will not be reviewed. Later-published science may be attached as an unrestricted PDF when the objection clearly explains its connection to the environmental analysis.
Taken together, the bottleneck is reliable notice plus a usable record: the right page, the right date, the earlier comment, and proof of a timely filing.
Watch next
Implementation now becomes the test. The first projects run under the revised process will show how consistently Forest Service pages surface deadlines, documents, subscription options, and filing instructions. Watch whether participants can find the authoritative page before the first clock expires, and whether objections are set aside because of timing, format, or weak links to earlier comments.
The rule covers certain Forest Service projects and activities under 36 CFR part 218. It does not govern every federal environmental review, and this card describes the process rather than offering legal advice.
Source
Forest Service, USDA, “Project-Level Predecisional Administrative Review Process,” final rule, FR Doc. 2026-20890, published October 13, 2026, effective November 12, 2026. https://www.federalregister.gov/documents/2026/10/13/2026-20890/project-level-predecisional-administrative-review-process