Texas approves ERCOT's Batch Zero for large loads
Recorded event: 2026-06-18
The Public Utility Commission of Texas approved ERCOT’s Batch Zero process for connecting large electricity users. ERCOT’s September 14–15, 2026 board presentation reports that provisional classifications were provided to interconnecting transmission service providers on September 3. The presentation also reports a pause on energizing new large-load data centers and crypto facilities pending eligibility verification, audit and community-impact review. A provisional classification is not final admission or a connected load.
Record over time
- 2026-09-03 · ERCOT’s September 14–15 board presentation reports provisional classifications provided on September 3, 2026. Separately, it reports a pause on energization of new Large Load data centers and crypto facilities pending eligibility verification, audit and community-impact review. Classification does not establish final admission or delivery.
Limitations
- The September presentation reports provisional classifications, not final admission. Its studied-load totals are inconsistent, so the total capacity remains unclear.
No new connection is implied by this narrative record. Only separately reviewed connections are displayed.