Arizona regulators hold first data-center / large-load workshop and weigh a universal large-load tariff

Recorded event: 2026-04-16

The Arizona Corporation Commission held an initial workshop on large-load and data-center customers on April 16, 2026, in the docket opened in 2025 (E-00000A-25-0069). Per the Commission, participants agreed on the need for new or improved policies so data centers keep paying for new generation and infrastructure, and the Commission discussed a hybrid pathway that could include a universal large-load tariff alongside energy supply agreements. Presenters included Arizona Public Service (APS), Salt River Project (SRP), and Tucson Electric Power/UniSource Electric (TEP/UNSE).

Record over time

Limitations

No new connection is implied by this narrative record. Only separately reviewed connections are displayed.

Open this move on the map